The project is funded and starting
The investment decision is made, but there is no management structure, no procedures and no approved baseline.
Project Management Services A3
A project's outcome is set in its first months. We build the management frame — quantities, WBS, cost and schedule baselines, procurement plan, procedures and KPIs — before mistakes become irreversible.
How it is bought
We reply within 1 business day. A commercial proposal follows within 5 business days of the scoping meeting.
In substance
Most troubled projects were troubled from the outset: quantities unverified, a schedule drawn to fit an announced date, a budget assembled without a cost structure, procurement not planned around long-lead equipment. Start-up is the cheapest point at which to change a project's outcome.
The investment decision is made, but there is no management structure, no procedures and no approved baseline.
The completion date was announced before it was calculated. Logic, resources and critical path were never tested.
The estimate was built from analogues or an earlier design stage, with no cost breakdown structure.
Items with 6–18 month lead times are neither identified nor ordered, although they determine the start-up date.
We check bills of quantities and the estimate, build the cost breakdown structure and record assumptions and exclusions.
Work breakdown structure, a Primavera P6 baseline schedule with logic and resource validation, and a baseline budget.
Long-lead equipment identified, order dates back-calculated from installation readiness, procurement strategy set.
Risk register with schedule and cost impact, response plan, project KPI framework and reporting format.
Responsibility matrix, change control, document control and reporting procedures; kick-off with all project participants.
Deliverables
The specific documents, reports and management products that remain with the client.
The completion date is derived from logic and resources, not imposed from above.
Costs map to the WBS, which makes later plan/actual control and forecasting possible.
Long-lead items are ordered on time because dates are back-calculated from installation readiness.
Procedures and reporting are working at launch rather than introduced during a crisis.
FAQ
Not answered here? Write to us and we will respond on your case.
Typically 4–8 weeks depending on project size and the quality of the input data; up to 10 weeks for large industrial facilities.
If construction has been running for under 6–9 months and no baseline exists, Start-up remains effective. Where the slippage is deeper, a project audit is the correct entry point.
The client. We prepare and defend the baseline, including assumptions and risks; approval remains the investor's management decision.
Schedule, cost, progress and forecast: a defensible project status every month.
We manage the project on the owner's behalf — from the land plot to commissioning.
Owner-side project management: an integrated team, international methodology, auditable reporting.
Managing design: release schedule, interdisciplinary coordination, expert review, value engineering.
Tell us about the asset and the current stage — we will propose a working format and team composition. A commercial proposal follows within five business days of the meeting.
We reply within 1 business day. A commercial proposal follows within 5 business days of the scoping meeting.