Equipment was ordered too late
The start-up date slips because of deliveries even though construction readiness was achieved.
Project Management Services A6
Projects are lost in the contract and in the purchase order date, not on the site. We manage procurement and contracts so that equipment arrives on time and the contract protects the owner.
How it is bought
We reply within 1 business day. A commercial proposal follows within 5 business days of the scoping meeting.
In substance
Procurement on a capital project is scheduling, not buying. Long-lead equipment with 6–18 month lead times drives the start-up date more than construction productivity does. Contract work is delivered together with First in Law, the consortium's legal firm.
The start-up date slips because of deliveries even though construction readiness was achieved.
Responsibility for schedule and quality is diluted, retention and penalty mechanisms do not function, acceptance is loosely defined.
Bids are not comparable, evaluation criteria were never fixed, and the award cannot be justified.
The contractor is in delay but the legal consequences are neither recorded nor applied.
Additional works are agreed on site and enter payment certificates without justification or cost assessment.
Package split strategy, long-lead identification, award dates back-calculated from installation readiness.
Tender documents and bills of quantities, prequalification, bid normalisation, technical and commercial evaluation, negotiation.
Balanced contracts prepared with First in Law: scope, schedule, quality, acceptance, liability, warranties, retention.
Manufacturing progress tracking, vendor inspections and FAT, logistics and site acceptance.
Change register with justification and assessment, claim preparation and defence of the owner's position.
Deliverables
The specific documents, reports and management products that remain with the client.
Orders are placed against installation readiness rather than when somebody remembers them.
Comparable bids and a competitive procedure produce a genuine market price.
The contract contains mechanisms that actually control schedule, quality and liability.
Additional works are assessed before, not after, execution.
FAQ
Not answered here? Write to us and we will respond on your case.
Equipment with long manufacturing and delivery cycles, from 6 to 18 months: process lines, transformers, cranes, special valves. If these are not identified and ordered early, the start-up date is set by delivery rather than construction — and money can no longer accelerate it.
We run the full procedure: documentation, prequalification, evaluation, negotiation and contract preparation. The award decision and signature remain with the client — a defining element of the agency model.
INVECON handles the technical side — justification, calculations, recording facts, quantities and consequences. The legal work is performed by First in Law, the consortium's legal firm.
Contractor selection in 4–8 weeks: documents, prequalification, evaluation, contract.
A single managing contractor across engineering, procurement and construction management.
Owner-side project management: an integrated team, international methodology, auditable reporting.
Schedule, cost, progress and forecast: a defensible project status every month.
Tell us about the asset and the current stage — we will propose a working format and team composition. A commercial proposal follows within five business days of the meeting.
We reply within 1 business day. A commercial proposal follows within 5 business days of the scoping meeting.