Industrial & Manufacturing · Temirtau

Reconstruction of quenching tower 1, by-product coke plant

Reconstruction of an operating structure: condition survey, strengthening design, works in a limited window.

Reconstruction of quenching tower 1, by-product coke plant — Temirtau

Project at a glance

Client
Qarmet JSC
Location
Temirtau, Kazakhstan
Status
Completed
Year
Confidential — under NDA
CAPEX
Confidential — under NDA
Area
Confidential — under NDA

Challenge

Reconstruction of a structure operating in an aggressive environment: actual structural condition differs from the original design, the strengthening scope cannot be defined without survey, and the works must fit a limited process window.

Our role

From survey to handover: establishing actual structural condition, managing the strengthening design, and organising and supervising works to a compressed programme.

Scope

  • Structural condition assessment and load capacity evaluation
  • Design management for reconstruction and strengthening
  • Work planning around the process window
  • Construction management and contractor coordination
  • Technical supervision and quality control

Results

  • Strengthening scope defined by calculation rather than by inspection
  • Works completed within the process window
  • Quality verified by testing and covered-works certification

Services delivered on this project

Shall we discuss your project?

Tell us about the asset and the current stage — we will propose a working format and team composition. A commercial proposal follows within five business days of the meeting.

We reply within 1 business day. A commercial proposal follows within 5 business days of the scoping meeting.